THE PROBLEM

Rocking Slabs Damaging Equipment and Product

After years of heavy forklift traffic, shifting and rocking concrete slabs in the warehouse were causing equipment to bounce when crossing joint lines. Continued rocking destabilized the soil beneath the slabs, creating voids large enough that forklifts could fall through. Product was shifting mid-transport, and maintenance costs on forklift tires and equipment were climbing.

Damaged and cracked warehouse concrete floor at a loading dock
Stratalock technicians performing polymer injection with a laser level in the warehouse
THE SOLUTION

Precision Polymer Injection in a Single Weekend

Stratalock developed a targeted injection plan to stabilize over 44,000 sqft. of dock and staging area flooring. Polymer was injected throughout the treatment area with a laser level guiding the floor back to an even, stable surface. The full project was completed overnight during a weekend, start to finish in under 24 hours, with no interruption to the customer's business.

GET STARTED

Concerned About Your Foundation? We Can Help.

Get a free assessment from our geotechnical experts and discover how our deep soil injection can stabilize your foundation—fast.

Or Call: (855) 850-5625
Licensed & Insured Contractors
40+ Years Combined Experience
Minimal Disruption Guaranteed